First utility unit of SP Phase 13 refinery launched

First utility unit of SP Phase 13 refinery launched

The first utility unit of a refinery in Phase 13 of giant South Pars Gas Field in southern Iran has became operational, said the manager of the phase's development project.

Payam Motamed added the first air compressor of the refinery's unit No. 123 has also become operational as the first step towards launching the refinery, Shana reported.

He said this utility unit is crucial for the refinery to receive natural gas as its feedstock.

Motamed said the remaining utility units of the facility including raw water, water cooling, steam, nitrogen and electricity systems and divisions will be set up and become operational by late June.

Motamed also noted that the refinery will begin production by late September.

   